German company Voith will supply Site C turbines, government announces

The last complete set of turbines for a Peace River dam were built at a metal works in the Soviet Union and shipped to B.C. aboard a Yugoslav freighter. 

Forty years later, both of those countries have been wiped from the map, but B.C. is still in the turbine market. 

article continues below

On Wednesday, Premier Christy Clark announced the purchase of six 183-megawatt turbines for the Site C dam—one of a handful of remaining contracts on the mega project left to be tendered. 

The turbines will be supplied by German-based Voith Hydro, one of the world's largest manufacturer of hydroelectric generators. The contract is valued at $470 million, and includes the design and installation of the turbines and generating stations. 

She said the generating station would not fit in the dome of the B.C. Legislature, where the announcment was held. 

"The design and manufacturing of these units is highly specialized work," BC Hydro CEO Jessica McDonald said. "They have to be custom-designed for each hydroelectric facility."

Voith Canada is headquartered in Montreal. The company previously completed upgrades to the G.M. Shrum Generating station at the W.A.C. Bennett Dam. 

Voith CEO Bill Malus said 400 person-years of employment will come from the turbine installation, including work for as many as 150 union and non-union millwrights, electricians and boilermakers. He said the company would have local training opportunities in the Peace Region, adding Voith would rely on local subcontractors as much as possible. 

The announcement was attended by a number of union officials, including boilermakers and the International Brotherhood of Electrical Workers. 

'Epic' moving jobs of years past  

turbine
A Soviet-built turbine for the Peace Canyon Dam. - Archive photo

With the exception of a partial replacement of the W.A.C. Bennett Dam's turbines completed last year, much of the generating capacity on the Peace River is original hardware. 

Transporting the Soviet-built turbines to the Peace Canyon dam required an "epic" moving job, according to a 1978 report in the Globe and Mail. 

The first of four, 220-ton turbines arrived in Vancouver in July of that year from the Leningrad Metal Works. It was the beginning of a 1,600-kilometre moving job—including two mountain ranges—expected to cost $4 million at the time. 

The eight metre-wide waterwheels could not be transported by highway or rail, and made most of the journey by barge. Apex Movers of Burnaby were hired to haul the turbines to the dam site.  

From Vancouver, the turbines were loaded onto a 45-metre trailer parked on top of an ocean barge, which hauled its cargo to the Gardner Canal south of Kitimat. There, the convoy began the first leg of its overland journey, carrying the turbine to an arm of the Nechako Reservoir and loading it onto a portable barge.

Eventually, the turbine made it to the Bennett dam by way of Williston Lake. The last few miles to Site One, as Peace Canyon was called, were traversed on logging roads straightened and widened for the project. 

reporter@dcdn.ca 

© Copyright Alaska Highway News

Comments

NOTE: To post a comment you must have an account with at least one of the following services: Disqus, Facebook, Twitter, Google+ You may then login using your account credentials for that service. If you do not already have an account you may register a new profile with Disqus by first clicking the "Post as" button and then the link: "Don't have one? Register a new profile".

The Alaska Highway News welcomes your opinions and comments. We do not allow personal attacks, offensive language or unsubstantiated allegations. We reserve the right to edit comments for length, style, legality and taste and reproduce them in print, electronic or otherwise. For further information, please contact the editor or publisher, or see our Terms and Conditions.

comments powered by Disqus
Alaska Highway People's Choice 2019
Sign Up for our Newsletter!

Popular News

Lowest Gas Prices in Chetwynd, Dawson Creek, Fort Nelson, Fort St John, Tumbler Ridge
British Columbia Gas Prices provided by GasBuddy.com

Community Event Calendar


Find out what's happening in your community and submit your own local events.