Scrapping Site C a $3-billion hit to ratepayers: BC Hydro

BCUC to visit the Peace Region Sept. 30 to Oct. 2 to gather public feedback

The BC Utilities Commission will hold three meetings in the North Peace this fall for residents to give their input on the commission's review of the Site C dam. 

The commission will hold 11 community input sessions across the province starting Sept. 23 in Vancouver. The purpose of the meetings, the commission says, is to gather feedback on its preliminary report set for release Sept. 20.

article continues below

The commission will be in the North Peace starting Sept. 30 in Hudson's Hope at the Pearkes Centre. There will be two sessions in Fort St. John Oct. 1 and 2 at the Pomeroy Hotel. The three sessions will take place from 6 to 10 p.m.

The commission will also be making stops in Kamloops, Kelowna, Nelson, Prince George, Victoria, and Nanaimo. 

The commission is being tasked to study the economic viability of continuing construction on the $8.8-billion project, now two years into construction, based on current electricity supply and demand and its cost to ratepayers. 

A final report is due Nov. 1, with the new NDP  cabinet expected to make a decision by the end of the fall legislative session on Nov. 30. 

The commission received 69 submissions from the public and experts that the commission says will inform its preliminary report.

Chief among them is a submission from Dr. Harry Swain, who chaired the federal-provincial review panel that studied and held public hearings on the dam in 2013 and 2014. 

Swain, who has become an outspoken critic of the dam since it was approved by the previous Liberal government in 2014, says construction should be stopped unless the cost to complete is less than $2 billion. He also calls for the flood reserve on the Peace River to be lifted and expropriated properties returned.

"BC Hydro’s load forecasting is not remotely investment grade," Swain writes. 

"It consistently, and by large margins, over-estimates demand, and the overestimates get larger the farther out they go. They are utterly inadequate as the basis for multi-billion dollar decisions, and cannot be relied on for business planning purposes."

Conservation measures remain the cheapest source of electricity, Swain concludes, and that BC Hydro should "buy conservation up to the cost of new supply."

"Demand will not materialize at even the low limit of BC Hydro’s demand forecast," he writes.

"It will be many years before new supply for domestic purposes is necessary; when it is, there are numerous sources that are less expensive than Site C."

Termination, remediation would cost $1 billion, BC Hydro says

In its 866-page filing, BC Hydro says it has received more than 200 provincial and federal authorizations to build various aspects of the dam since it was approved and began construction in 2015. 

BC Hydro says $1.8 billion has been spent on the dam as of June 30, 2017, with expenditures due to reach $2.1 billion by the end of the year. Much of that has been spent on field and technical studies, land acquisitions, permit approvals, and entering into major construction contracts, Hydro says.

BC Hydro says it has entered into $4 billion in contracts. However, none of the construction contracts require termination payments or penalties, it says. 

"BC Hydro would still be accountable for costs associated with payments for contractor work to date and demobilization costs," Hydro writes.

Hydro estimates the cost of terminating work and remediating the dam site at $1 billion.

"This value represents BC Hydro’s best estimate based on the available information in the time permitted, and is subject to material uncertainty," it writes. "The scope of remediation would be determined in consultation with regulatory agencies and other stakeholders."

Coupled with its sunk costs, BC Hydro says a cancellation by the end of December would force a $3 billion write-off that it would look to collect from ratepayers in both short and long-term rate hikes—pending government or commission approval.

"In BC Hydro’s next revenue requirements application, which would relate to years after fiscal 2019, we would propose a time period over which the balance … would be recovered in rates," the company writes.

Hydro estimates suspending the project and restarting before 2024 would cost $1.2 billion with two years of ramp-up time needed before construction could restart.

"Suspension introduces significant risk for restarting the project," it says. "If the project restarts, it would cost more and could take longer to complete."

Hydro maintains the project is on time and on budget, with a contingency budget of more than $800 million, and a year of "schedule contingency" to manage cost overruns and delays.

"Though there remain risks to project execution in the future, BC Hydro expects to complete Site C within the existing budget and on the current schedule," it writes.

It also maintains that new energy and capacity resources are needed within the next decade, with or without LNG. 

"Our need for new capacity is particularly pressing. It arises within 10 years, regardless of whether any of the proposed LNG projects in British Columbia proceed," it writes.

Submissions to the inquiry can be read in full by clicking here.

editor@ahnfsj.ca

© Copyright Alaska Highway News

Comments

NOTE: To post a comment you must have an account with at least one of the following services: Disqus, Facebook, Twitter, Google+ You may then login using your account credentials for that service. If you do not already have an account you may register a new profile with Disqus by first clicking the "Post as" button and then the link: "Don't have one? Register a new profile".

The Alaska Highway News welcomes your opinions and comments. We do not allow personal attacks, offensive language or unsubstantiated allegations. We reserve the right to edit comments for length, style, legality and taste and reproduce them in print, electronic or otherwise. For further information, please contact the editor or publisher, or see our Terms and Conditions.

comments powered by Disqus
Sign Up for our Newsletter!

Popular News

Lowest Gas Prices in Chetwynd, Dawson Creek, Fort Nelson, Fort St John, Tumbler Ridge
British Columbia Gas Prices provided by GasBuddy.com

Community Event Calendar


Find out what's happening in your community and submit your own local events.