Seventy-two workers were laid off from the Site C dam project last week because of a safety-related work stoppage caused by an old landslide, officials say. 

Movement at an old landslide on the north bank of the Peace River, where slope excavation work is ongoing, has forced the work stoppage.

article continues below

BC Hydro says there has been recent slope movement around a pre-existing slide on the north bank of the Peace River. 

“The Peace River Valley has many pre-existing slides and the design of the excavation on the north bank is planned so that all historic slides in the dam site area will be completely removed by excavation work,” spokesman David Conway said in a statement. 

“Recently, there was some slope movement in an area of a known pre-existing slide. Work was stopped while a plan was developed to safely remove the slide. Engineers have already reviewed this slide to ensure the excavation can continue safely and we expect work to resume shortly.”

Peace River Hydro Partners spokeswoman Amber Harding confirmed the layoffs. Most of the 72 workers who were laid off were heavy equipment operators and labourers, she said.

There is no timeline on when work will resume, Harding said.

“The layoff is not the same as a termination,” Harding said. “We may provide future opportunities for these workers once the crack has been addressed.”

Peace River Hydro Partners has more than 1,300 workers still on site, Harding said.

Josh Pastoor, regional director for the Christian Labour Association of Canada in Fort St. John, dismissed rumours the layoffs were the result of the new NDP minority government and its plans to have the $8.8-billion dam project reviewed.

“We’re hoping they can get back to work soon, there’s nothing immediate beyond that,” he said.

“I’ve had a lot of direct questions about that (the NDP government and review), and it’s a fair question to ask.”

editor@ahnfsj.ca

© Copyright Alaska Highway News

Comments

NOTE: To post a comment you must have an account with at least one of the following services: Disqus, Facebook, Twitter, Google+ You may then login using your account credentials for that service. If you do not already have an account you may register a new profile with Disqus by first clicking the "Post as" button and then the link: "Don't have one? Register a new profile".

The Alaska Highway News welcomes your opinions and comments. We do not allow personal attacks, offensive language or unsubstantiated allegations. We reserve the right to edit comments for length, style, legality and taste and reproduce them in print, electronic or otherwise. For further information, please contact the editor or publisher, or see our Terms and Conditions.

comments powered by Disqus
Alaska Highway People's Choice 2019
Sign Up for our Newsletter!

Popular News

Lowest Gas Prices in Chetwynd, Dawson Creek, Fort Nelson, Fort St John, Tumbler Ridge
British Columbia Gas Prices provided by GasBuddy.com

Community Event Calendar


Find out what's happening in your community and submit your own local events.